Fort Lauderdale-Hollywood International Airport Terminal 3 BHS/CBIS

GRAEF provided engineering services as part of a design-build team for a new Checked Baggage Inspection System (CBIS) and Baggage Handling System (BHS) in Terminal 3 at Fort Lauderdale-Hollywood International Airport (FLL), supporting JetBlue Airways operations.

The project involved the design and construction of new facilities, along with strategic modifications to existing spaces and systems. GRAEF’s scope included structural, mechanical, plumbing, fire protection, and civil engineering services to support the installation of a high-capacity in-line baggage screening system capable of processing up to 3,200 bags per hour. Additional improvements included a new outbound baggage handling system and extensive underground utility modifications to accommodate the new infrastructure.

Given the active airport environment, the team implemented detailed phasing and coordination strategies to minimize disruptions to airline operations and passenger flow, ensuring a seamless integration of new systems into the terminal’s daily functions.

Other Projects

IMG_6415

Destin-Fort Walton Beach Airport BHS Expansion

MOY06412AJPG

Milwaukee Mitchell International Airport Concourse D Jet Bridges

IMG_1857

Destin-Fort Walton Beach Airport Ticketing Terminal Expansion

IMG_6135

Miami International Airport Building 3089 (Park 8) 40/50 Year Recertification

IMG_5297 Edited

Miami International Airport FedEx Cargo Distribution Center Expansion

Aerial

Austin-Bergstrom International Airport Baggage Handling System

Location

Fort Lauderdale, FL

 

Project Data

$35 Million Project Cost

 

GRAEF Services

Civil Engineering
Mechanical Engineering
Structural Engineering

Fort Lauderdale-Hollywood International Airport Terminal 3 BHS/CBIS Contacts